Up to date information regarding the restoration of steam locomotive 6029 in Canberra, ACT Australia. Beyer Garratt 6029 is an EX NSWGR locomotive and was a member of the largest, and most powerful class in Australia. The restoration to full working order is being undertaken by volunteers in Canberra.
6029 is owned by the Australian Railway Historical Society, ACT Division and the restoration is proudly supported by their tourist operations and by the generous donations of members and public supporters.
The society operates rail tours out of Canberra with our heritage fleet of steam and diesel locomotives and rolling stock every few weeks.
To travel in style on any of our tours, or to learn more about our collection and operations, go to Canberrarailwaymuseum.org
Jun 18, 2012
Sunday 17 June 2012
The installation of the coupling and connecting rods continued on the right hand leading engine unit. These components were originally crack tested and assessed a few years back and while in storage, had developed the usual layer of surface rust. This was easily was polished off while the locking split pins were fitted to the castellated lock nuts on the coupling rods before the team turned its attention the largest component being the connecting rod. This is a one piece forging that is over ten feet long. The roller bearing was given one last clean out and inspection, then after an initial team meeting (how are we going to do this), the rod was fitted into place. As the rod is very heavy, and we are undercover and without any form of crane, a system of rollers and levers were deployed. To the teams amazement, this task was completed with relative ease. It seems that Mr. Isaac Newton actually did know a thing or two, and not sleeping through the all those physics lectures many years ago actually paid off. Thanks to David, Tony and Patrick for the elbow grease used to polishing the rods. Only three sets to go boys!
Back over in the cab, Andy continued with the fitting of the timber roof lining. This job has to be completed before the electrical conduits can be fully fitted, but more importantly, completion will allow the fitting of the whistle cords. Andy has been working on this job between workdays and estimates that it will be completed in the next month.
Ian and his team have also been working in the cab area, but in this case it’s all under the floor. The myriad of pipes and valves that control the stoker motor continue to be fitted, all be it with continued reference to the original drawings. Ian has copied the pipe drawing and used colored pencils to sort out what goes where.
The front tank is almost ready for the vital water test with only a blanking plate to be fitted in place . This job will have to be done in the mid-afternoon the allow ice to thaw... It is, after all, the middle of winter here.
Alan Gardner
Jun 5, 2012
Saturday 2 June 2012
The 6029 management team recently met to review the project plan against the original Gantt chart. In general terms we are tracking well, and the large inventory of stripped components is reducing in size as they are progressively refitted to the locomotive. It is estimated that about 10% of the inventory is still to be fitted, however this means the 90% is fitted ready for operation. From a personal perspective, I am delighted with the high standard of work that the team has achieved, and a testament to this can be seen in the photos posted every month. Some recent examples have been the Nathan mechanical lubricators, the air compressor and now the stoker motor. All have been completely stripped down to the last nut and bolt and been rebuilt better than new using the best materials available and to the highest possible standard. Another pleasing fact is that as the team rebuilds these sub-assemblies they are in fact becoming content experts on steam technology of the 1950’s. This expertise means that the end product that we are now realizing is something that the team can be very proud of.
Our extended network of help, led by our friends at Goodwin Alco has also helped the project significantly. The cab now looks as good as new, infact 80% of the cabs sheets are new, including the seats, new timber window frames and safety glass. The roof is presently being re-lined with cedar boards and yes, once again with help from Goodwin Alco.
The main focus of work in the winter months will be the fitting of the coupling and connecting rods followed soon after by the valve gear. Again the team is becoming very proficient at fitting the components of steam technology. However the fitting of the forged connecting rods will be facilitated with the use of contemporary lifting equipment.
We are now at a stage where the obvious question is being asked, when will 6029 be back in steam? Putting aside an end date guestimate, the answer will be in a review of what we still have to complete. That Gantt chart still lists the ash pan, boiler cladding sheets, smoke box, steam piping, electrical system and the stoker trough, not to mention all of the small bore copper piping that is required to complete the brake system.
The big news is that we will be holding another super week on a date yet to be advised. For those who don’t know, we take a holiday from our day jobs to spend a full week working on 6029. A bit of a conundrum for the project manager, as he has now been appointed the museums general manager full time.
Regards
Alan Gardner
May 22, 2012
The coupling and connecting rods have been crack tested and the polishing is realising good results. The driving wheels have been lined up and the locomotive was moved forward for about four feet to facilitate the best position for the eventual fitting of the coupling rods.The valve gear fit out is progressing, but we will need more willing hands to help progress what could be called arduous work.
The cab fit out is gaining momentum with a small team lead by our resident expert, Ian. The myriad of steam and air pipes are slowly going back together and the pile of stored pipes is getting smaller every workday. Graeme has worked out the best way to refit the control valves for the air compressor and the blower control with the fitting of the spindles (20 foot long) that run from the cab thought the boiler hand rail connecting to the vales attached at the smoke box end.
Our next workday is Saturday 2 June all welcome. Winter woollies will be essential.
Alan Gardner
Apr 24, 2012
Quiet Progress
If you have been following the blog for a while, you may remember the quality of the work he did on the mechanical lubricators , and it comes as no surprise that his next restoration task is being carried out to the same standard. Ian, and Glenn Bridgart have been hard at work on the stoker motor and Cardew valves, all of which have suffered from the years in service and years in open storage.
The Cardew valves, used to prevent damage from any excess water in the cylinders, being mostly brass, have suffered very little and look a treat now that they are clean, but the springs inside them are a different story and may require replacement before too long.
The stoker motor is also getting the royal treatment and while it is complete, and was not seized by exposure, is going to need a little work to set it right. The crank will need to have the journals chrome plated to repair some pitting and the piston rods will likely get the same treatment. Otherwise it has cleaned up very well and no doubt will give sterling service when it is finished.
A little work has been done on the front tank, and another day or so should see its underside completed and ready to fit. One badly corroded area of the floor will have to be replaced, but better now than when it is full of water and on the loco. David slaved away for hours removing the years of grease and grime that had accumulated under the tank, with a fair bit of elbow grease and some determination. Well done, its not the most glamorous job, but it still needs to be done.
Last but not least, there are a few images this monthof 3016 leaving Goulburn roundhouse after the maintenance work had been completed nearby.
Remember that the next workday is Saturday the 5th of May at the Canberra Museum, jobs for everyone and if your lucky, a BBQ lunch as well
Mike Reynell
Mar 16, 2012
Workday Cancelled
Feb 22, 2012
Sunday 19 February 2012
Ian was seen under the boiler cradle installing the newly completed blow down muffler that is piped to the two blowdown valves either side of the boiler. Ian advises that he still has to disassemble the whole system for final painting and then re-fit.
Paul and Carl had to squeeze under the smoke box to re-fit the exhaust ball joint from the leading engine unit. The joint itself was spotlessly cleaned some time ago and after a re check it was again proved ok to fit. The four 7/8 BSW bolts were tightened and finished off with the split pins. While in this area they also had a go at fitting the live steam ball joint to the leading unit. With all of theses task now completed the team is looking forward to standing up straight in the smoke box, and because of their effort,s the fit out of the blast pipe and the live steam pipes can now start. Oh did we mention that we still have to hand lap all those lens rings before we can fit the pipes.
The leading tank was at long last moved out of storage by a crane contractor and placed on stands to allow for cleaning of the underside before fitting. While on the stands all of the plumbing that facilitates water feed and draining have been dusted off and trial fitted.
Our next work day in on Saturday the 3rd of March and if we get a good turn out we will prep the leading tank for final fitting soon after.
Alan Gardner
Feb 10, 2012
The valve gear and coupling rods were taken out of storage and are being checked for fit and final assembly. The coupling rods were hard grease lubricated and the residual grease is very hard to remove but the condition of all pins and bushing suggest that it did the job well. The polishing and crack testing of the rods will take quite a few workdays to complete but this work is necessary to ensure that no defects are present. The smoke box fit out is continuing with the unenviable task of lapping the lense rings that make the steam tight joint between the main steam pipes . Carl and Andy had a go with two rings almost good to go and we estimate we only have about 12 to go.... just in the smoke box area. Keep going guys! The leading tank will now be transferred to the front of the shed with the use of an external crane contractor. Some preparation work is still to be completed on the mounting pads at the bottom of the tank. Our next work day will focus on the leading water tank to ensure that it will be ready for final fitting to the leading unit soon there after. Alan Gardner
Jan 30, 2012
Weekday Progress
Ian Senini has been working on the lubrication systems for some time, and did a wonderful job of restoring the mechanical lubricators for us. He has spent some time during the last weeks getting the lubrication lines connected and ready for test, and last week was able to prime all the lines and check for leaks. This achievement means that the front tank will soon be put back on permanently.... and then, given that there are two engine units, he will start on the hind unit.
From the collection of Howard Moffat, here is a picture he took in 1979 of a tour 6029 hauled on the Michalego line. Wont be long and it will be possible to take picture like it once again.

Jan 16, 2012
Sunday 15 January 2012
The steam pipes that run from the super heater header inside the smoke box were next in the critical path and as usual they had to be cleaned up for assessment. The flange spherical faces that make up the steam tight joint were wire brushed and the tedious job of lapping each face commenced. Many of the old bolts were seized in place and had to be heated to red hot before being driven out. All new bolts have been ordered well in advance ready for fitting of the pipes but we still are a few workdays away from this.
The sand box fit out continued with three of the four leading, sand traps, air connections and pipes fitted. Some of the pipes required re setting and welding for alignment, but this task is made easy with the oxy torch and sledge hammer. This work is being completed before the leading tank is fitted into place as it is easer to do this with un-restricted access.
Thanks to Ian, the testing of the leading lubrication system will now take place mid week between workdays. A test pressure gauge will be fitted to what is called the terminal check valves that is located in close proximity to each cylinder. Once pumped up to just below 225 psi all lube lines will be visually examined for leaks, and any pipes that need repair will be fixed as required. After the integrity of the pipes and lubricators is proven the system will be flushed through and primed. This will have to be done again before the steam tests commence but the hard to get at pipes will be good to go one the tank is in place.
Our next workday will be an interesting one as we will be prepping the leading tank for final fit and if all goes to plan, 6029 will be shunted out of the shed for the fitting of the tank.
Alan Gardner
Jan 10, 2012
With everyone ready to go it was soon realized that the smoke box door would not open past 20 deg as it was fouling a very large nut that adjusts the boiler cradle pivots. After some minor adjustment the door was clear to open and the elements were soon being pushed into what is called the flue tubes. Once in position a very large tee clamp bolts is fitted and secured with a 1" BSW nut. The first element took about one hour to fit and by mid afternoon this was down to about ten minutes from start to finish. The down side being that it was getting very hot by mid afternoon so it was decided to stop with just 6 elements to go. This decision was also influenced by the fact that we are 4 tee bolts short. Needless to say that the sourcing of tee bolts is the highest priority on the shopping list.
The last of the rebuilt sand boxes was fitted into place and the sand delivery pipes have been dusted off from storage. They are bent in all directions to clear the wheels and brake gear but once marred up to the adjacent box the fit is quite obvious. The sand traps x 8 are progressively being cleaned out and air tested before final fit and once fitted the crew looks forward to filling them with sand for the fist time in many years.
Our next workday is Sunday the 15th of January, all welcome.