6029 is owned by the Australian Railway Historical Society, ACT Division and the restoration is proudly supported by their tourist operations and by the generous donations of members and public supporters.
The society operates rail tours out of Canberra with our heritage fleet of steam and diesel locomotives and rolling stock every few weeks.
To travel in style on any of our tours, or to learn more about our collection and operations, go to Canberrarailwaymuseum.org

Feb 22, 2012

Sunday 19 February 2012

The clean up of the coupling rods and valve gear continues with the crew getting well organised with a production line set up. David starts of the process with the de-greaser and scraper to remove the residual hard grease and road grime. Next Howard gives each rod the once over with the eclectic powered wire bush flowed by David with the polishing wheels and the end result speaks for itself. When completed each rod is stored adjacent to the locomotive ready for final fitting.



Ian was seen under the boiler cradle installing the newly completed blow down muffler that is piped to the two blowdown valves either side of the boiler. Ian advises that he still has to disassemble the whole system for final painting and then re-fit.

Paul and Carl had to squeeze under the smoke box to re-fit the exhaust ball joint from the leading engine unit. The joint itself was spotlessly cleaned some time ago and after a re check it was again proved ok to fit. The four 7/8 BSW bolts were tightened and finished off with the split pins. While in this area they also had a go at fitting the live steam ball joint to the leading unit. With all of theses task now completed the team is looking forward to standing up straight in the smoke box, and because of their effort,s the fit out of the blast pipe and the live steam pipes can now start. Oh did we mention that we still have to hand lap all those lens rings before we can fit the pipes.

The leading tank was at long last moved out of storage by a crane contractor and placed on stands to allow for cleaning of the underside before fitting. While on the stands all of the plumbing that facilitates water feed and draining have been dusted off and trial fitted.

Our next work day in on Saturday the 3rd of March and if we get a good turn out we will prep the leading tank for final fitting soon after.

Alan Gardner

Feb 10, 2012

Saturday 4th February 2012 The critical path work for the leading engine units is now all but complete with the lubrication system now tested. Ian continued to check and double check all of the copper pipes and he also identified some pinch points that may lead to failures further down the track. Rectifing these points will include extra brackets to will stop the pipes from vibrating or working loose. The lubricator drives from the valve gear is now fitted and the end result speaks for itself.

The valve gear and coupling rods were taken out of storage and are being checked for fit and final assembly. The coupling rods were hard grease lubricated and the residual grease is very hard to remove but the condition of all pins and bushing suggest that it did the job well. The polishing and crack testing of the rods will take quite a few workdays to complete but this work is necessary to ensure that no defects are present. The smoke box fit out is continuing with the unenviable task of lapping the lense rings that make the steam tight joint between the main steam pipes . Carl and Andy had a go with two rings almost good to go and we estimate we only have about 12 to go.... just in the smoke box area. Keep going guys! The leading tank will now be transferred to the front of the shed with the use of an external crane contractor. Some preparation work is still to be completed on the mounting pads at the bottom of the tank. Our next work day will focus on the leading water tank to ensure that it will be ready for final fitting to the leading unit soon there after. Alan Gardner