Mark and Alan started the fit up of the air compressor's Nathan mechanical lubricator and associate pipe work. Tony continued to dot around the locomotive with black paint as it seems we had missed few spots, it is over 100 feet long!
Back at the cab end Graeme Kidgell completed the installation of the fireman’s side boiler feed lines. Andy Heys prepped the last of the cab mounting bolt holes and also had time to sneak in a few cups of tea. You just cant get good help theses days!
By days end we received news that the Eveleigh team had almost finished the cab and that one more day should do it.
All being well the cab will be back in Canberra before then end of the month and will go straight onto the locomotive. Updates will be posted as the details firm up.
Alan Gardner