Up to date information regarding the restoration of steam locomotive 6029 in Canberra, ACT Australia. Beyer Garratt 6029 is an EX NSWGR locomotive and was a member of the largest, and most powerful class in Australia. The restoration to full working order is being undertaken by volunteers in Canberra.
6029 is owned by the Australian Railway Historical Society, ACT Division and the restoration is proudly supported by their tourist operations and by the generous donations of members and public supporters.
The society operates rail tours out of Canberra with our heritage fleet of steam and diesel locomotives and rolling stock every few weeks.
To travel in style on any of our tours, or to learn more about our collection and operations, go to Canberrarailwaymuseum.org
Jul 12, 2009
Superweek Report
Monday morning 7:30 am -4 degrees. The first job as the highest priority was to light the fire. In fact this would be repeated every morning.
As planned the boiler cradle strip down was completed and the usual undercoat and two top coats of black were applied. The reversing gear was completely seized and the rollers that facilitate easy movement had in fact worn flat when the locomotive was in operation. A compete new set of rollers is being manufactured. The pivot centre oil lines and boxes were repaired and fitted ready for use. The re fit steam delivery pipes from the smoke box to the hind unit started, however we have to order a new set of inch BSW studs and nuts to complete the job. Thanks to the efforts of Mike Ridley, Peter Gleeson, Stuart Edwards, Barry Peffer and Roger Maynard.
On the engine unit side the first of the four bogies was completely stripped down to the last nut and bolt. The lessens learnt here is that even the sub assemblies are heavy. The bogie frame was cleaned down and crack tested with no significant issues found. Three of the manganese horn liners will be replaced due to cracking in the corners. The many smaller components were progressively stripped cleaned and assessed. As previously reported the lateral control springs are in poor condition and by weeks end they were dispatched to Sydney for rebuild. Thanks to Ian Senini, Malcolm Cluett and David Griffiths.
In all 290 hours of work was completed for the week realising another significant milestone. Thanks to the efforts of all involved the boiler cradle is now almost compete. We can now move onto the overhaul of the four bogies and when completed reassembly of the locomotive proper will commence. In parallel the bogie work we will continue with the strip down of the motion and the assessment of the engine units.
We are now at what can be called the turning point of the project, however as is always the biggest threat to the project is money. We now have some big ticket items that will have to be competed in the next six months. These are,
· 20 off super heater elements. $27,000.
· Hard chroming of piston and valve rods.$ 12,000.
· Spring repairs and rebuilds. $10,000.
· Piston rings for vales, cylinders and air compressor . $14,000.
· Sundries. $20,000.
So now for the big news, if we realise the above $89,000 6029 will be steaming in 2011. We have the team and the skills to do the job, so it all gets down to money, its as simple as that. So please keep the donations coming in, no matter how small every bit counts. Collectively we can once again see Australia’s largest stem locomotive gracing the rail network.
Keep steaming,
Alan Gardner
Jul 6, 2009
Superweek 2009 has started
Saturday 4 July Workday
Report from Peter Reynell
Another successful day, made the more memorable because it was the 33rd anniversary of the Garratt’s first trip under ARHS ACT Accreditation. And we had a little party to celebrate. Lindsay Richmond [another survivor of those early days] and I reminisced over some slides [yes, even a projector was used!] and about 25 people from the various work parties on site were shown the good old days and a good time…our ARHS on train catering crew including Chris S and Lindy S put on a much better than usual spread. Imagine Roast Beef, Oven baked Chicken fillet, party pies and salad , as well as hot doggies; sausages and all the accomaniements.And even cake!
Thanks, crew, you did us proud.
A special thanks to Brian Nye, Chief Executive of the Australasian Railway Association for coming along to offer some very encouraging words.
Oh, and we did some work too..ends were rescued from the old superheater elements, more black paint went on the boiler cradle and Paul Quinn lit a huge fire under the engine unit which eventually liberated the very frozen solid pony truck bearing which caused the angst months ago when the pony truck came off the rails. A long overdue apology to Lindsay, we always chose to blame his trackwork..sorry, Oldmate. (Some did, some knew better...Mike)
Work on the bogies has commenced with the front units hind bogie receiving attention. The lateral control springs from all four bogies should be in Sydney by the end of the week to be overhauled while the crew work on the bogies.
Jun 28, 2009
Like a house of cards
Saturday morning saw Mike Riddley, Mike and Peter Reynell turn up to take advantage of the comfortable work area in the Eveleigh large erecting shop.
Today saw more than a little progress on the cab. In the past, nearly all the work has concentrated on removing years of built up corrosion and muck from the panels so that the damage can be identified and assessed.
We finally have given up trying to do the repair work in situ, and the decision was made to reduce the cab to smaller sub-assemblies so that the panels can be repaired properly and the corrosion that has until now been trapped between the riveted components can be removed properly.
With a few rows of rivets and bolts removed, the cab quickly fell apart like a heavy house of cards. The rear panel of the cab took five or six people to lift onto trestles.
The roof vents were also liberated from the roof panel so that they can be repaired separately before being refitted to the new roof.
Over the next few weeks, replacement components will be arranged so that the corroded areas can be removed and new metal welded back in. There is a new roof to be cut and rolled, the angles that mount the cab to the loco frame will need to be replaced, and some paneling around the windows will need attention.
It seems like a lot of work, considering that it just a cab, but once it is finished, I doubt it will need to be touched for another 20 or 30 years.
Jun 22, 2009
Sunday 21 June 2009
Jun 19, 2009
Jun 15, 2009
a nice shade of grey..
Jun 14, 2009
Progress report..... Saturday 13 June
IN Canberra the rear bunker has been sandblasted and undercoated in a trendy shade of grey by a contractor, so there is another painting job.
Photos when they come to hand.
Next Canberra work Day SUNDAY 21 June
Jun 7, 2009
Saturday 6 June Canberra workday
Tasks undertaken included:
- more pressure washing, now about half way finished on the front engine unit; thanks again, Roger
- more painting, thanks Stu
- cross compound air compressor dismantled, with some challenges, including the b*****y thing creating a vacuum which made the removal of one piston a challenge; thanks Ian, Shaun, Shane and all the other expert advisers.
- removal of the pivot bearing at the front end of the boiler cradle; thanks to Marc, Kyle and John [and again, more experts]
Alan Gardner
Al's mate Graham Kidgell from the little railway near Melbourne
Peter Reynell
Shane Bollard
Shaun Barker
Ian Senini
Marc Millar
Mike Ridley
Stu Edwards
Kyle Rollinson
John Kempton
Roger Maynard
Also on site were Lindsay Richmond, who made lunch, thanks Oldmate; Paul Quinn, vibrating on a bogie frame;
Andy D, Jack Barker, Gav W. ; Dave and Keith Malcolm lighting 3016 for todays' Bungendore train, and David Villiers as cleaner and polisher.
Next workdays
- at Eveleigh..Saturday 13 June...contact peter@project6029.com for access and job details.
- at Kingston [Canberra Railway Museum] Sunday 21 June