Jul 12, 2009

Superweek Report

Brrrrrrrrrrrr...

Monday morning 7:30 am -4 degrees. The first job as the highest priority was to light the fire. In fact this would be repeated every morning.



As planned the boiler cradle strip down was completed and the usual undercoat and two top coats of black were applied. The reversing gear was completely seized and the rollers that facilitate easy movement had in fact worn flat when the locomotive was in operation. A compete new set of rollers is being manufactured. The pivot centre oil lines and boxes were repaired and fitted ready for use. The re fit steam delivery pipes from the smoke box to the hind unit started, however we have to order a new set of inch BSW studs and nuts to complete the job. Thanks to the efforts of Mike Ridley, Peter Gleeson, Stuart Edwards, Barry Peffer and Roger Maynard.

On the engine unit side the first of the four bogies was completely stripped down to the last nut and bolt. The lessens learnt here is that even the sub assemblies are heavy. The bogie frame was cleaned down and crack tested with no significant issues found. Three of the manganese horn liners will be replaced due to cracking in the corners. The many smaller components were progressively stripped cleaned and assessed. As previously reported the lateral control springs are in poor condition and by weeks end they were dispatched to Sydney for rebuild. Thanks to Ian Senini, Malcolm Cluett and David Griffiths.

In all 290 hours of work was completed for the week realising another significant milestone. Thanks to the efforts of all involved the boiler cradle is now almost compete. We can now move onto the overhaul of the four bogies and when completed reassembly of the locomotive proper will commence. In parallel the bogie work we will continue with the strip down of the motion and the assessment of the engine units.

We are now at what can be called the turning point of the project, however as is always the biggest threat to the project is money. We now have some big ticket items that will have to be competed in the next six months. These are,

· 20 off super heater elements. $27,000.
· Hard chroming of piston and valve rods.$ 12,000.
· Spring repairs and rebuilds. $10,000.
· Piston rings for vales, cylinders and air compressor . $14,000.
· Sundries. $20,000.

So now for the big news, if we realise the above $89,000 6029 will be steaming in 2011. We have the team and the skills to do the job, so it all gets down to money, its as simple as that. So please keep the donations coming in, no matter how small every bit counts. Collectively we can once again see Australia’s largest stem locomotive gracing the rail network.

Keep steaming,

Alan Gardner

Jul 6, 2009

Superweek 2009 has started

The July superweek has started and there has been a good turnout with the promise of a few more participants later in the week.

Saturday 4 July Workday

Report from Peter Reynell

Another successful day, made the more memorable because it was the 33rd anniversary of the Garratt’s first trip under ARHS ACT Accreditation. And we had a little party to celebrate. Lindsay Richmond [another survivor of those early days] and I reminisced over some slides [yes, even a projector was used!] and about 25 people from the various work parties on site were shown the good old days and a good time…our ARHS on train catering crew including Chris S and Lindy S put on a much better than usual spread. Imagine Roast Beef, Oven baked Chicken fillet, party pies and salad , as well as hot doggies; sausages and all the accomaniements.And even cake!
Thanks, crew, you did us proud.

A special thanks to Brian Nye, Chief Executive of the Australasian Railway Association for coming along to offer some very encouraging words.

Oh, and we did some work too..ends were rescued from the old superheater elements, more black paint went on the boiler cradle and Paul Quinn lit a huge fire under the engine unit which eventually liberated the very frozen solid pony truck bearing which caused the angst months ago when the pony truck came off the rails. A long overdue apology to Lindsay, we always chose to blame his trackwork..sorry, Oldmate. (Some did, some knew better...Mike)

Work on the bogies has commenced with the front units hind bogie receiving attention. The lateral control springs from all four bogies should be in Sydney by the end of the week to be overhauled while the crew work on the bogies.

Jun 28, 2009

Like a house of cards


Saturday morning saw Mike Riddley, Mike and Peter Reynell turn up to take advantage of the comfortable work area in the Eveleigh large erecting shop.

Today saw more than a little progress on the cab. In the past, nearly all the work has concentrated on removing years of built up corrosion and muck from the panels so that the damage can be identified and assessed.

We finally have given up trying to do the repair work in situ, and the decision was made to reduce the cab to smaller sub-assemblies so that the panels can be repaired properly and the corrosion that has until now been trapped between the riveted components can be removed properly.

With a few rows of rivets and bolts removed, the cab quickly fell apart like a heavy house of cards. The rear panel of the cab took five or six people to lift onto trestles.

The roof vents were also liberated from the roof panel so that they can be repaired separately before being refitted to the new roof.

Over the next few weeks, replacement components will be arranged so that the corroded areas can be removed and new metal welded back in. There is a new roof to be cut and rolled, the angles that mount the cab to the loco frame will need to be replaced, and some paneling around the windows will need attention.

It seems like a lot of work, considering that it just a cab, but once it is finished, I doubt it will need to be touched for another 20 or 30 years.

Jun 22, 2009

Sunday 21 June 2009


The start to the day was significantly delayed due very wet conditions that did not clear until midday. After the weather cleared David and Alf salvaged the useful parts off the unserviceable super heater elements.

Barry Peffer having returned from his overseas work, was reunited with the needle gun on the boiler cradle. Shaun Barker continued with the strip down and assessment of the front pivot. Gavin and Paul jacked up and removed the first of the four bogies revealing many years of grime and rust. As a result of this the leading unit is now a 4,8,0 and will soon be an 0,8,0. As suspected the lateral control springs will have to be send out for reconditioning.

Peter went out on the local steam train to Bungendore to sell raffle tickets, thanks Peter! Bruce drove down from Sydney to measure up the compressor bores confirming that they are within specification. Bruce also gave us a look at the great work he is dong with the power reverser and has promised some photos for the blog.

Our next work day is Saturday the 4th of July and Super week will start on Monday the 6th of July.

Alan Gardner.

Attendees...

Alan Gardner
Peter Reynell
Gavin Woolf
Paul Quinn
Shaun Barker
Jake Barker
Barry Peffer
David Villiers
Alf Spiteri

Jun 19, 2009

There has been some new content added to the history channel...Check it out here

Jun 15, 2009

a nice shade of grey..


The contractors have been in and completed the sandblasting and priming of the bunker, and what a difference it makes!

Jun 14, 2009

Progress report..... Saturday 13 June

AT Eveleigh; in the Large Erecting Shop, "Cabin Boy" Ron Denholm and I liberated some 55 year old rust from the area around the Firemans side door and window where the outside plating had buckled from the internal pressure. Fortunately the frame work has not deteriorated as much as has the plate work, so repair will be relatively easy.

IN Canberra the rear bunker has been sandblasted and undercoated in a trendy shade of grey by a contractor, so there is another painting job.

Photos when they come to hand.

Next Canberra work Day SUNDAY 21 June

Jun 7, 2009

Saturday 6 June Canberra workday

Another fantastic turnout, another productive day..although the wind chill factor in the afternoon reminded us that it IS winter, and that 40 degree celsius summer is now behind us.

Tasks undertaken included:
  • more pressure washing, now about half way finished on the front engine unit; thanks again, Roger
  • more painting, thanks Stu
  • cross compound air compressor dismantled, with some challenges, including the b*****y thing creating a vacuum which made the removal of one piston a challenge; thanks Ian, Shaun, Shane and all the other expert advisers.
  • removal of the pivot bearing at the front end of the boiler cradle; thanks to Marc, Kyle and John [and again, more experts]
AND , to show that we do not only pull things apart, the compressor was test fitted to the smokebox to prove that the new support plate will work.

In attendance:
Alan Gardner
Al's mate Graham Kidgell from the little railway near Melbourne
Peter Reynell
Shane Bollard
Shaun Barker
Ian Senini
Marc Millar
Mike Ridley
Stu Edwards
Kyle Rollinson
John Kempton
Roger Maynard
Also on site were Lindsay Richmond, who made lunch, thanks Oldmate; Paul Quinn, vibrating on a bogie frame;
Andy D, Jack Barker, Gav W. ; Dave and Keith Malcolm lighting 3016 for todays' Bungendore train, and David Villiers as cleaner and polisher.

Next workdays
  • at Eveleigh..Saturday 13 June...contact peter@project6029.com for access and job details.
  • at Kingston [Canberra Railway Museum] Sunday 21 June
The next Superweek is planned to commence on the 4th of July, the anniversary of the first workday, and then 6-10th of July.

May 30, 2009

MHG Workvan

Barry Peffer has been working to clean up the MHG brake van to prepare it for our use as a work and breakdown van. Here are a few pictures showing his progress. The pictures as usual are taken by Howard Moffat, our staff photographer, who is doing a great job of recording the faces and progress being made on this project.

May 28, 2009

Thursday 28th May 2009.

The quiet achievers. 

Work has been progressing between our weekend workdays at a steady pace. We now have 30 brand new superheater elements installed thanks to Gavin and Ian. David Malcolm  has arranged to borrow an element tester from our friends at the RTM. This will facilitate the high pressure testing of the required 20 elements that will have to be re conditioned. This  will make up the complete  set of 50. We will also take the opportunity to repair and test the spare elements while we have the test equipment on site.

Ian has also completed the rebuild on the bottom smoke box front plate and has now moved onto the replacement bracket and plate work for the air compressor mount. If this is not enough Ian is also making the new the sheet metal pockets for the wash out plugs at home. Well done and a big thankyou to Ian.

Between his bus driving shifts, Stuart has been dropping in to apply the many coats of paint required on the boiler cradle. Thanks to his efforts and the weekend crew  we should see the boiler cradle work completed in June. A great team effort.

After the boiler cradle we intend to start work on the four bogies as we are already  aware that the lateral control springs will require a rebuild. Typically when bogies are stripped down all of the working components tend to yield a lot of work for all concerned. So we anticipate many hours of crack testing, weld repair and even replacement of some components.

The air compressor strip down has commenced with the bottom cover removed. Again 20 plus years of inaction has every bolt resisting until the last turn. It was planned to send out the two piston rods for hard chroming, however a close inspection has revealed that the railways applied this previously.

The regulator rod will be sent out for hard chroming shortly, as when the fitting of the  superheater elements is completed the regulator will have to be fitted to facilitate the  planed hydrostatic and steam tests.

Our next workday is Saturday 6 June. Yes winter already.

Alan Gardner