Up to date information regarding the restoration of steam locomotive 6029 in Canberra, ACT Australia. Beyer Garratt 6029 is an EX NSWGR locomotive and was a member of the largest, and most powerful class in Australia. The restoration to full working order is being undertaken by volunteers in Canberra.
6029 is owned by the Australian Railway Historical Society, ACT Division and the restoration is proudly supported by their tourist operations and by the generous donations of members and public supporters.
The society operates rail tours out of Canberra with our heritage fleet of steam and diesel locomotives and rolling stock every few weeks.
To travel in style on any of our tours, or to learn more about our collection and operations, go to Canberrarailwaymuseum.org
Feb 22, 2012
Sunday 19 February 2012
Ian was seen under the boiler cradle installing the newly completed blow down muffler that is piped to the two blowdown valves either side of the boiler. Ian advises that he still has to disassemble the whole system for final painting and then re-fit.
Paul and Carl had to squeeze under the smoke box to re-fit the exhaust ball joint from the leading engine unit. The joint itself was spotlessly cleaned some time ago and after a re check it was again proved ok to fit. The four 7/8 BSW bolts were tightened and finished off with the split pins. While in this area they also had a go at fitting the live steam ball joint to the leading unit. With all of theses task now completed the team is looking forward to standing up straight in the smoke box, and because of their effort,s the fit out of the blast pipe and the live steam pipes can now start. Oh did we mention that we still have to hand lap all those lens rings before we can fit the pipes.
The leading tank was at long last moved out of storage by a crane contractor and placed on stands to allow for cleaning of the underside before fitting. While on the stands all of the plumbing that facilitates water feed and draining have been dusted off and trial fitted.
Our next work day in on Saturday the 3rd of March and if we get a good turn out we will prep the leading tank for final fitting soon after.
Alan Gardner
Feb 10, 2012
The valve gear and coupling rods were taken out of storage and are being checked for fit and final assembly. The coupling rods were hard grease lubricated and the residual grease is very hard to remove but the condition of all pins and bushing suggest that it did the job well. The polishing and crack testing of the rods will take quite a few workdays to complete but this work is necessary to ensure that no defects are present. The smoke box fit out is continuing with the unenviable task of lapping the lense rings that make the steam tight joint between the main steam pipes . Carl and Andy had a go with two rings almost good to go and we estimate we only have about 12 to go.... just in the smoke box area. Keep going guys! The leading tank will now be transferred to the front of the shed with the use of an external crane contractor. Some preparation work is still to be completed on the mounting pads at the bottom of the tank. Our next work day will focus on the leading water tank to ensure that it will be ready for final fitting to the leading unit soon there after. Alan Gardner
Jan 30, 2012
Weekday Progress
Ian Senini has been working on the lubrication systems for some time, and did a wonderful job of restoring the mechanical lubricators for us. He has spent some time during the last weeks getting the lubrication lines connected and ready for test, and last week was able to prime all the lines and check for leaks. This achievement means that the front tank will soon be put back on permanently.... and then, given that there are two engine units, he will start on the hind unit.
From the collection of Howard Moffat, here is a picture he took in 1979 of a tour 6029 hauled on the Michalego line. Wont be long and it will be possible to take picture like it once again.

Jan 16, 2012
Sunday 15 January 2012
The steam pipes that run from the super heater header inside the smoke box were next in the critical path and as usual they had to be cleaned up for assessment. The flange spherical faces that make up the steam tight joint were wire brushed and the tedious job of lapping each face commenced. Many of the old bolts were seized in place and had to be heated to red hot before being driven out. All new bolts have been ordered well in advance ready for fitting of the pipes but we still are a few workdays away from this.
The sand box fit out continued with three of the four leading, sand traps, air connections and pipes fitted. Some of the pipes required re setting and welding for alignment, but this task is made easy with the oxy torch and sledge hammer. This work is being completed before the leading tank is fitted into place as it is easer to do this with un-restricted access.
Thanks to Ian, the testing of the leading lubrication system will now take place mid week between workdays. A test pressure gauge will be fitted to what is called the terminal check valves that is located in close proximity to each cylinder. Once pumped up to just below 225 psi all lube lines will be visually examined for leaks, and any pipes that need repair will be fixed as required. After the integrity of the pipes and lubricators is proven the system will be flushed through and primed. This will have to be done again before the steam tests commence but the hard to get at pipes will be good to go one the tank is in place.
Our next workday will be an interesting one as we will be prepping the leading tank for final fit and if all goes to plan, 6029 will be shunted out of the shed for the fitting of the tank.
Alan Gardner
Jan 10, 2012
With everyone ready to go it was soon realized that the smoke box door would not open past 20 deg as it was fouling a very large nut that adjusts the boiler cradle pivots. After some minor adjustment the door was clear to open and the elements were soon being pushed into what is called the flue tubes. Once in position a very large tee clamp bolts is fitted and secured with a 1" BSW nut. The first element took about one hour to fit and by mid afternoon this was down to about ten minutes from start to finish. The down side being that it was getting very hot by mid afternoon so it was decided to stop with just 6 elements to go. This decision was also influenced by the fact that we are 4 tee bolts short. Needless to say that the sourcing of tee bolts is the highest priority on the shopping list.
The last of the rebuilt sand boxes was fitted into place and the sand delivery pipes have been dusted off from storage. They are bent in all directions to clear the wheels and brake gear but once marred up to the adjacent box the fit is quite obvious. The sand traps x 8 are progressively being cleaned out and air tested before final fit and once fitted the crew looks forward to filling them with sand for the fist time in many years.
Our next workday is Sunday the 15th of January, all welcome.
Dec 12, 2011
Saturday 3rd December 2011
Nov 25, 2011
Sunday 20 November 2011
Malcolm and his daughter had a go at cleaning out the residual mess of grease and grime from where the stoker trough was once fitted. It seems that the grease points that are situated outside of this area were never checked to see if the lines were actually delivering the grease where it was designed to go. The end result was years of congealed grease mixed with coal dust forming great lumps of crud. They also had a go at applying some long over due grey primer to the top deck above the hind water tank.
David continued with the rebuild of the crinoline bands that will support the fitting of the boiler cladding sheet metal. The boiler now sports several horizontal string lines that will help align the boiler bands correctly. The myriad of counter sunk screws that hold all of the bands in place have had to be rebuilt as many of the tapped holes had rusted out. As the bands are only ¼” thick a new nut has been welded into place under each side to make up for the poor thread.
During recent weeks, Alan has also been working to remove the life expired electrical cables from their conduits all over the loco. The insulation has hardened from years of exposure to the heat of a steam engine, and likely also from the temperature extremes from years of outside storage in Canberra. As such, all the wiring on the loco will be replaced, in some cases with new technology to help us work safely into the future. You can see from some of the pictures just how bad some of the wiring is.
Alan Gardner
Oct 24, 2011
Yep, that's right.... Our next workday will involve a foreign order and even better a trip across the border.
Lindsay has asked for some help with some track work in Queenbeyan, so we are going to take
edit 26/10/2011.. I have just been advised that 3016 will be providing the motive power for the trip, so there is even more reason to come along for the trip....
Volunteers are welcome and we will be leaving from the Canberra Museum platform at 8.30AM, do a little track work on the turntable road in Queenbeyan and then should be back for lunch at 1pm. Come for the ride and get in a little exercise as well! It should be fun.
Oct 21, 2011
While the cab was being worked on, the motion was also getting some attention, with Mal starting to polish the rods in readiness for crack testing and refitting. There are a lot of them, so this work will continue for some weeks.
Oct 5, 2011
Saturday 1 October 2011
At the opposite end of the boiler, the smoke box is stating to fill up with the pipes that connect to the air compressor and the blower. Both of these components are fed with steam from the superheater header which itself is also receiving some final attention with throttle cam and valves soon to be refitted. Once that is done, the control linkage that runs from the header back to the drivers cab will be fitted.
6029 is fitted with what is called a front end throttle. Put simply the control of steam from the boiler takes place at the front in the smoke box and is controlled by the driver back at the cab end via a system of levers and rods. It was a much more efficient system when compared to the more traditional system inside the boilers dome.
For a few years now we have been completing the rebuild of many smaller components only to put them into storage awaiting final fitment. Now that the locomotive is under cover, theses components can be fitted. Ian delivered the first of the four mechanical lubricators (right hand leading) and with the help of a few strong arms it was lifted into place. The lubrication feed pipes are now being cleaned out one by one and with some head scratching, the stamped identification acronyms are actually starting to make sense.
The move into the shed however, does not come without some pain, as the team headed by John and Kyle started moving over the many tools, benches and storage cupboards. Having said that, Saturdays weather was very wet and generally unpleasant but being indoors at long last meant a happy and dry team could continue to work in comfort.
Alan Gardner