Up to date information regarding the restoration of steam locomotive 6029 in Canberra, ACT Australia. Beyer Garratt 6029 is an EX NSWGR locomotive and was a member of the largest, and most powerful class in Australia. The restoration to full working order is being undertaken by volunteers in Canberra.
6029 is owned by the Australian Railway Historical Society, ACT Division and the restoration is proudly supported by their tourist operations and by the generous donations of members and public supporters.
The society operates rail tours out of Canberra with our heritage fleet of steam and diesel locomotives and rolling stock every few weeks.
To travel in style on any of our tours, or to learn more about our collection and operations, go to Canberrarailwaymuseum.org
Jun 15, 2009
a nice shade of grey..
Jun 14, 2009
Progress report..... Saturday 13 June
IN Canberra the rear bunker has been sandblasted and undercoated in a trendy shade of grey by a contractor, so there is another painting job.
Photos when they come to hand.
Next Canberra work Day SUNDAY 21 June
Jun 7, 2009
Saturday 6 June Canberra workday
Tasks undertaken included:
- more pressure washing, now about half way finished on the front engine unit; thanks again, Roger
- more painting, thanks Stu
- cross compound air compressor dismantled, with some challenges, including the b*****y thing creating a vacuum which made the removal of one piston a challenge; thanks Ian, Shaun, Shane and all the other expert advisers.
- removal of the pivot bearing at the front end of the boiler cradle; thanks to Marc, Kyle and John [and again, more experts]
Alan Gardner
Al's mate Graham Kidgell from the little railway near Melbourne
Peter Reynell
Shane Bollard
Shaun Barker
Ian Senini
Marc Millar
Mike Ridley
Stu Edwards
Kyle Rollinson
John Kempton
Roger Maynard
Also on site were Lindsay Richmond, who made lunch, thanks Oldmate; Paul Quinn, vibrating on a bogie frame;
Andy D, Jack Barker, Gav W. ; Dave and Keith Malcolm lighting 3016 for todays' Bungendore train, and David Villiers as cleaner and polisher.
Next workdays
- at Eveleigh..Saturday 13 June...contact peter@project6029.com for access and job details.
- at Kingston [Canberra Railway Museum] Sunday 21 June
May 30, 2009
MHG Workvan
May 28, 2009
Thursday 28th May 2009.
May 18, 2009
Workday Report 18 May 2009
Friday 15 May.
Gavin and Ian held their regular Friday session with the installation of 10 new superheater elements. Lindsay Richmond also helped out with the heavy lifting, thanks Lindz. The last job for the day was to lift the smoke box front plate into position.
Saturday 16May
The Eveleigh work team removed the life expired roof off the cab revealing many years of rust and subsequent damage. Mike will complete a full set of CAD drawings to outsource the construction of new roof sheets.
Sunday 17 May.
The installation of the smoke box front plate was completed by Ian and old mate Alan Kent. The bottom plate attachment was yielding some problems, however Ian has assured us that it will be sorted out next week. After the last of the new elements were removed from the storage van, Marc started to clean of each ball end for installation next Friday.
The donated workbenches were reassembled and we now have four workstations that will assist with the repair and rebuild of the many small components. Gavin has sourced a six inch vice that we can install on one of the benches. Wow!!
The Boiler cradle is staring to look like a new one as Stuart, Howard, and just about everyone is having a go with the re paint. Gavin and Peter removed the water delivery pipes revealing some active corrosion that will require some major surgery.
Our next work day will be Saturday the 6th of June and work will continue on the boiler cradle.
We will now be holding weekly workdays every Friday, so if you have the time to help out please come along . Lunch is BYO and Gavin will be supervisor for all mid week work and if you intended coming along please let him know in advance.
Alan Gardner.
The Cab in Eveleigh
Sunday 17 May
Alan Gardner
Gavin Woolf
Alan Kent
Marc Millar
Stuart Edwards
Ian Senini
Alf Spiteri
David Villiers
Kyle Rollinson
Vince Patrech
John Kempton
Peter Anderson
Peter Reynell
and Howard Moffat
I will leave it to Al to list the days achievements...this post is to recognise those who were there yesterday.
a big weekend
You ask why?
Even in Canberra's relatively dry climate, the enemy of all things steel appears. In this case, the worst parts are the window cut outs where the gutters naturally collected, but not necessarily diverted rain, and areas near the doors where two or three layers of plate are now interspersed with oxidised steel.
Best to fix it "proper" now; roof off will give better access.
And the roof itself is a maze of holes where everything that could be hung, was. Even the ceiling was held up [or down] by a bolt through the roof.Actually, many bolts.
Then, more holes for the colonial conversion to dual control. Another heavy casting, more holes in the roof.
May 4, 2009
Saturday 2nd of May 2009
Many of the boiler cladding sheets for the back head are in poor condition and Gavin’s new plasma cutter was put to good use for the first time. Marc and Ted experienced the joys of sheet metal work and a result the back head sheets are now about 90% complete.
Back in Sydney Mike Reynell is organising the manufacture of 50+ element washers and when completed we can start installing the new elements. As usual Bruce s continuing with the machining of the many replacement components.
Our next workday is Sunday the 17th of May starting at about 9 am, all welcome!
Alan Gardner