Aug 18, 2014

6029 is now back in the shed having run the 200km round trip to Goulburn. The purpose of the run was to complete the necessary signal interface testing. Goulburn is controlled by signal circuits and it had to be proven that the locomotive can be seen on the track and that it activates the interface circuits. The good news is that the signals engineer was happy with the results and the testing will now move onto the next stage of the plan.

We stabled overnight in Goulburn workshops and it was a very cold start to say the least, at minus five degrees C. Getting out of a warm bed at 5 am was not a good start but the light up crew had to start even earlier. The reward was the start of the run at 8am with the exhaust steam putting on a spectacular sight as we left Goulburn on the way home.



The two day run was a succession of testing and gradually increasing the speed as each test parameter was proven. The last part of the run home was at full speed and we are happy that all went well. Having said that we still have a way to go but at this stage it’s a cautious thumbs up at this point.

We have received some criticism that we were not able to advertise in advance that we would be out on the network. We don’t apologies for this as the testing is a critical element of ensuring and demonstrating that all is well to network and industry standards. We have advertised on our web page that tickets will be on sale soon but we can’t pencil a firm date until the notification of change is completed including testing and network registration.

I have been asked "how do you guys seem to just get the job done with no fuss" both in terms of the rebuild and the roll out of operations. The fact is I am very fortunate to lead a team that is well qualified in engineering, training and operations. That’s not to say things won’t go wrong as they most certainly do and often when you least expect them. Having a team that can fix the issue whatever it might be is critical, but the key word is team.

So what's next? For me, it’s countless more hours in front of a computer completing all the required documentation. We have a full load adhesion load test planed on the Canberra branch in the next few weeks. Again this won’t be advertised and we would like to remind all to please observe the network rules of trespass.

The first runs will be on the Canberra branch and tickets will be available at http://canberrarailwaymuseum.org/ . If you are interested, regularly check our web page and this blog for details as they come to hand.

Our next workday is Saturday 6 September at the museum. Please keep an eye on the web page for advanced ticket sales and please support us by purchasing a ticket or several.