6029 is owned by the Australian Railway Historical Society, ACT Division and the restoration is proudly supported by their tourist operations and by the generous donations of members and public supporters.
The society operates rail tours out of Canberra with our heritage fleet of steam and diesel locomotives and rolling stock every few weeks.
To travel in style on any of our tours, or to learn more about our collection and operations, go to Canberrarailwaymuseum.org

Feb 25, 2009

Sunday 22 February 2009 

The critical work path was the main focus of the day . Gavin almost competed the installation of the smoke box floor and the blast pipe can now be temporarily fitted to facilitate the final fitting of the smoke stack.  The old boiler cladding sheets were test fitted around the firebox area to facilitate the measuring up of new pieces. This work is being brought forward to ensure the cab can be lifted straight onto the boiler when delivered from Sydney. Howard, Michael and Barry continued with the cleaning and painting of the boiler cradle. Michael levelled the boiler cradle and it now sit true on the stands.   As usual Peter cooked a delightful lunch and gave the site a much need clean up.


Our next workday will be on  Saturday the 7th of March. Work will continue  on the cradle and replacement boiler. We still have to make up four timber supports for the boiler cradle to facilitate  the fitting of boiler onto the cradle. After this vital milestone is reached, the fit out of the feed water system and fire grate will commence, when completed  we will steam test the boiler.

Alan Gardner

Feb 19, 2009

A CORRECTION

Humbly, a correction..our next Canberra work day is Sunday 22 February 2009; and yes,it is out of pattern because whilst we all like 6029 working with her on Valentines day was seen by some to be an abberation!

Also, due to the kindness of our Sydney hosts, there will be a Cab work day at Eveliegh on Saturday 21 February.

Feb 13, 2009

Interested in a little Garratt history?

MOSI (Museum of Science & Industry) in Manchester, England, is celebrating 100 years since the development of one of the world’s most successful steam locomotives with a new archive display on Beyer-Garratts. Click Here for more information.

Feb 8, 2009

Not a cool workday; Saturday 7 February 2009

Well, we have worked through the extremes of Canberra's weather, yesterday must have been near 40 degrees Celsius.

But Alan got off to an early start, still cussing whoever did the stationary boiler modifications..but most of that is now behind us, studs that had been removed from the foundation ring have now been replaced, preparatory to re-installing the ash pan. And other fire box fittings are being placed on the replacement boiler, but no thought of steaming yesterday as it was a total fire ban day.

Peter got up close and personal [and early] with some piping under the cab which carries steam to the stoker motor. Surprisingly, one line still contained water.

Ted Coulter drove the new air driven needlegun to paint that I applied way back in 1973/4[,there is a product endorsement sponsorship opportunity here]; Howard Moffat applied a coat of red [same product] to the front engine buffer beam casting and Vince and new worker Mike Ridley[welcome Mike] ground and scraped, and painted wheels and boiler cradle till the weather was just too hot. David Carroll grabbed what he thought might be the coolest task, operating the Steam cleaner, but his reward was to become very dirty. Just hope the can clean up before Valentine's day.

Next workday..Third Sunday, which is 21 February.

For those that have been following the project and the photos of the work taken by Howard, take a look at the photos taken today... In just two weeks the worksite has transformed, so much so that some may think they are no longer looking at a Garratt.

And a note from Alan

Critical path work 
Many jobs are being carryout in parallel as labour permits; however the highest priority work is classified as critical path. The term critical path in the sequence or order of work ensures that the overall project is completed in the most cost effective manner at the earliest completion date. With this type of project work specific tasks are carried out in parallel rather than sequentially. Thanks to the efforts of many people off site work is being completed and will be available for assembly as the project progress. To give and example the cab, power reverser, stoker engine are all offsite being overhauled as part of the boiler and cradle works. 

Onwards and forward
With all of the above in parallel tasks progressing the replacement boiler and the cradle will be the focus.  Within the next few months these two major components will be joined together in preparation for the final steam test. However funds are tight and before we can complete this major mile stone we will need to raise about $5,000, so could I ask you all to dig deep and ensure that we can steam 6029 sooner rather than later. For tax deductible donations go to the link at the top of this blog page. 
So if we can raise the funds we can complete the following.
Smoke box & boiler
1. Install the replacement floor.
2. Repair and fit super heater /smoke box cover.
3. Remove smoke box door plate 
4. Repair and install super heater header and fittings.
5. Fit all ash pan / foundation ring mounting studs.
6. Fit all cleading sheets and insulation to blackhead.
Boiler cradle 
1. Strip clean and repair frame as required 
2. Make and fit additional cradle support stands 
3. Level main cradle 
So as you can see from the above if we can keep the attendance   up at the work day we will have a progressive and exciting year ahead. 

Alan Gardner  

Feb 7, 2009

Awsome Meccano

Most us played with Meccano when we were young, but this note and pics from England show some of what you really can do with Meccano!

Hi Alan,
I would like to submit some photographs of my recent construction of an Meccano model representation of  AD60 no. 6029 in 2.5ins gauge. The mid red and mid green is correct for Binns road, Liverpool, Lancs. Meccano of the period 1946 -1956/57 and entirely appropriate to the early fifties AD60 heavy freight batch articulated locomotives construction period in my native Lancahire at the Beyer Peacock works in West Gorton Manchester. 

I have fitted the laterboiler bogie brakes and the extended bunker.
I have purposely omitted the acoustic enhancement piping for alerting crews to warning detonators placed on track.

I offer it as encouragement to the volunteer team engaged on the project to have her in working condition by 2014 for the New South Wales Railway Centenary celebrations.

A true leviathan of steam weighing in at 260tons in working order.

Special Thanks:
A copy of this e-mail is sent to 'Meccanoman' Dave Taylor of Great Dunmow, Essex, UK, for his supply of various special items and to my dearest sister Elaine Fairhurst and her husband Harry of Mount Eliza, Victoria, Aus, for their support with literature and an DVD of 6029 in action.

Best of luck meanwhile with the project.

Tom Martland

Tom adds in a follow-up mail that the model is driven by a motor in the coal bunker space, and the driving wheels have a coupled braking arrangement...

Feb 3, 2009

A REMINDER

that our next workday at the Canberra Railway Museum is Saturday 7 February 2009; come earl if you wish as the weather man is promising a hot day. Bring water, a hat and suncream, and a cheap paintbrush.

Come one, come all..join in the fun...