Andy Heys put his carpentry skills to the test building all new timber packing’s that acts as an interface between the engine unit and the front water tank. The finished job looked so good that it will be a pity to paint over the new wood. Work was also taking place at ground level with the fitting of the right hand leading valve gear including the radius rod and expansion link with its die block. Many of the old tapered locking pins have been assessed as unserviceable but replacements are no longer available and the final fit of the valve gear cannot take place until the pins are manufactured new. Regardless, it was still pleasing to actually fit the polished valve gear into place.
The smoke box fit out continued with Graeme Kidgell fitted 22 of the 44 7/8 BSW saddle bolts that secure the smoke box to the boiler cradle. This job has not been an easy one as many of the bolt holes were welded over when the boiler was used at the saw mill in Victoria. The welded over holes had to be cut out with the use of a small pilot drill and oxy touch as they welded material was almost glass hard. A finish off with the die grinder and the bolts were tightened up with the good old torque gun.... only 22 to go!
The next few workdays will continue around the leading engine unit with the testing and commissioning of the oil lubrication system and some minor cosmetic work around the cylinders. Once completed the leading tank will be final fitted into position and inturn the water system hook up will commence with gusto.
Alan Gardner